dc.contributor | Gil Rodríguez, Carmen Cecilia | |
dc.creator | Azurin Huari, Eliane Kimberly | |
dc.date.accessioned | 2024-02-06T16:34:26Z | |
dc.date.accessioned | 2024-05-09T20:04:39Z | |
dc.date.available | 2024-02-06T16:34:26Z | |
dc.date.available | 2024-05-09T20:04:39Z | |
dc.date.created | 2024-02-06T16:34:26Z | |
dc.date.issued | 2023-11-10 | |
dc.identifier | https://hdl.handle.net/20.500.12557/6050 | |
dc.identifier.uri | https://repositorioslatinoamericanos.uchile.cl/handle/2250/9393921 | |
dc.description.abstract | La metodología BIM ha experimentado una notable expansión en la actualidad, siendo
ampliamente adoptada por entidades públicas y privadas, además de contar con una marcada
presencia en el ámbito académico. En este contexto, el Gobierno Peruano ha demostrado su
compromiso mediante la creación del Plan BIM Perú en el año 2019, desde entonces se ha
avanzado considerablemente en la definición de las pautas, apéndices, proyectos piloto y metas
específicas, con el propósito de promover la gradual adopción de BIM en el sector de la
construcción.
La presente tesis tiene como objetivo analizar la aceptación y uso de la metodología BIM de
los profesionales de la construcción de la región del Cusco, según el modelo de la Teoría
unificada de aceptación y uso de la tecnología (UTAUT, por sus siglas en inglés).
El alcance de esta investigación es descriptivo, adoptando un diseño no experimental de corte
transversal. La población bajo estudio son los Ingenieros Civiles colegiados en el Colegio de
Ingenieros del Perú Consejo departamental del Cusco. Para la muestra, se ha seleccionado un
grupo de 358 Ingenieros Civiles de esta población, utilizando un método de muestreo no
probabilístico basado en la conveniencia.
Para verificar las hipótesis formuladas, se empleó el modelado de ecuaciones estructurales
mediante el método de mínimos cuadrados parciales (PLS-SEM) haciendo uso del software
estadístico SmartPLS 4.
Para este fin, se evaluó el modelo de medición mediante las cargas factoriales de los
indicadores, la fiabilidad de la construcción mediante el alfa de Cronbach y la fiabilidad
compuesta, la validez convergente a través de los valores de AVE “varianza promedio extraída”
y la validez discriminante mediante el criterio de Fornell & Lacker, todos estos valores
superaron el umbral requerido para su aceptación.
Como paso final, para verificar las relaciones hipotéticas planteadas, se realizó un análisis de
Booststrapping. Mediante el cual se determinaron los valores estadísticos T y valores P, los
cuales fueron mayores a 1.96 y menores a 0.05, respectivamente, para que las hipótesis
planteadas fueran aceptadas.
La investigación logró determinar que el nivel de uso actual de la metodología BIM en la región
Cusco es de 23.18%. Según el ciclo de vida de adopción de innovaciones, este porcentaje coloca a la región en la fase de “adaptadores tempranos”, avanzando hacia la etapa de “mayoría
temprana”.
Al aplicar el enfoque del modelo UTAUT a la metodología BIM, se ha establecido que las
variables independientes: “expectativa de esfuerzo”, “expectativa de rendimiento” e “influencia
social” influyen en la variable dependiente: “intención de uso de la metodología BIM”. Además,
se ha identificado que la variable independiente “condiciones facilitadoras” influye en la
variable dependiente “comportamiento de uso de la metodología BIM”. Por otro lado, se
observó que la variable independiente “actitud” no tiene un efecto significativo en las variables
“influencia de uso ni en el comportamiento de uso de la metodología BIM”. | |
dc.description.abstract | The BIM methodology has experienced a notable expansion at present, being widely adopted
by public and private entities, in addition to having a marked presence in the academic field. In
this context, the Peruvian Government has demonstrated its commitment through the creation
of the BIM Peru Plan in 2019, since then progress has been made with great capacity in the
definition of guidelines, sighed, pilot projects and specific goals, with the purpose of Promote
the gradual adoption of BIM in public investment projects.
The objective of this thesis is to analyze the acceptance and use of the BIM methodology by
construction professionals in the Cusco region, according to the Unified Theory of Technology
Adoption and Use (UTAUT) model.
The scope of this research is descriptive, adopting a non-experimental cross-sectional design.
The population under study are the Civil Engineers registered in the College of Engineers of
Peru Departmental Council of Cusco. For the sample, a group of 358 Civil Engineers from this
population has been selected, using a non-probabilistic sampling method based on convenience.
To verify the formulated hypothesis, the structural equations model was used through the partial
least squares method (PLS-SEM) using the SmartPLS 4 statistical software.
For this purpose, the measurement model was evaluated through the factor loadings of the
indicators, the reliability of the construction through Cronbach's alpha and the composite
reliability, the convergent validity through the AVE values "extracted average variance" and the
discriminant validity using the Fornell & Lacker criterion, all these values exceeded the
threshold required for acceptance.
As a final step, to verify the proposed hypothetical relationships, a Booststrapping analysis was
performed. Through which the statistical values T and P values were determined, which were
greater than 1.96 and less than 0.05, respectively, so that the proposed hypotheses have been
recognized.
The investigation was able to determine that the current level of use of the BIM methodology
in the Cusco region is 23.18%. Based on the innovation adoption life cycle, this percentage
places the region in the “early adopter” phase, moving towards the “early majority” stage.
By applying the UTAUT model approach to the BIM methodology, it has been established that
the independent variables: effort expectation, performance expectation and social influence
influence the dependent variable: intention to use the BIM methodology. In addition, it has been identified that the independent variable facilitating conditions influences the dependent variable
behavior of use of the BIM methodology. On the other hand, it was observed that the
independent variable attitude does not have a significant effect on the use influence variables
or on the behavior of using the BIM methodology. | |
dc.language | spa | |
dc.publisher | Universidad Andina del Cusco | |
dc.publisher | PE | |
dc.rights | https://creativecommons.org/licenses/by-nc-nd/4.0/ | |
dc.rights | info:eu-repo/semantics/openAccess | |
dc.subject | Tecnología UTAUT | |
dc.subject | Building Information Modeling BIM | |
dc.subject | Modelamiento de ecuaciones estructurales | |
dc.title | Análisis de la aceptación y uso de la metodología BIM de los profesionales de la construcción de la región Cusco según el modelo UTAUT, 2023. | |
dc.type | info:eu-repo/semantics/bachelorThesis | |