dc.contributorTeves Rojas, Augusto
dc.creatorLozano Levano, Jimmy Gregory
dc.creatorLozano Levano, Jimmy Gregory
dc.date2017-09-06T21:30:49Z
dc.date2017-09-06T21:30:49Z
dc.date2016
dc.date.accessioned2022-12-06T19:45:54Z
dc.date.available2022-12-06T19:45:54Z
dc.identifierhttp://hdl.handle.net/20.500.14076/4580
dc.identifier.urihttps://repositorioslatinoamericanos.uchile.cl/handle/2250/5277765
dc.descriptionLa mina Casapalca durante el transcurso de los 10 últimos años ha ido implementando diferentes tecnologías en las diferentes áreas del proceso productivo minero, tales como método de minado, perforación, voladura, acarreo en interior mina, extracción de mineral, ventilación, etc; logrando a la fecha altos índices de productividad los mismos que se nota en la reducción de costos directos de operación; y actualmente se encuentra realizando trabajos en el ámbito de tajeos donde la separación de niveles de perforación de los Taladros Largos han sido incrementados de 19 metros a 25 metros, reduciendo de esta manera los costos en preparación de tajeos. La presente tesis muestra una metodología para el diseño del método de minado Sub Level Stoping, abarcando el análisis geomecánico de la roca caja y del mineral, el análisis operativo del ciclo de minado y la evaluación económica del método de minado, lo que conlleva siempre a buscar la mejora continua en todos los procesos mineros que integran la mina Casapalca. Hoy en día, para hacer el cambio de método de explotación, es de suma importancia el monto del capital de inversión requerido; es necesario así mismo ejecutar un proceso de selección del método de explotación mina mediante un análisis sistemático de todas las variables que intervienen en un proyecto minero para evaluar su rentabilidad a largo plazo.
dc.descriptionThe Casapalca mine during the course of the past 10 years has been implementing different technologies in different areas of mining , including mining method , drilling, blasting , hauling inside the mine , ore mining , ventilation, etc. production process ; achieved to date high productivity the same as it shows in the direct reduction of operating costs; and it is currently doing work in the field of stopes where the separation of drilling levels of the long drills have been increased from 19 meters to 25 meters, thus reducing costs in preparation stopes. This thesis demonstrates a methodology for the design of mining method Sub Level Stoping , covering the geomechanical analysis of the host rock and ore , operating mining cycle analysis and economic evaluation of mining method , which always leads to seek continuous improvement in all processes, of the Casapalca mine . a selection process mining exploitation method using a systematic analysis of all the variables involved in a mining project to evaluate its long-term profitability. Today, for the change in method of operation is paramount the amount of capital investment required ; so it is necessary to run
dc.descriptionTesis
dc.formatapplication/pdf
dc.languagespa
dc.publisherUniversidad Nacional de Ingeniería
dc.rightsinfo:eu-repo/semantics/restrictedAccess
dc.rightshttp://creativecommons.org/licenses/by-nc-nd/4.0/
dc.sourceUniversidad Nacional de Ingeniería
dc.sourceRepositorio Institucional - UNI
dc.subjectMétodos de minado
dc.subjectMétodo Sub Level Stoping
dc.subjectDiagnóstico del ciclo de minado
dc.subjectAnálisis de costos
dc.titleAplicación del método Sub Level Stoping con taladros largos en cuerpo Mery Unidad Minera Americana-Compañía Minera Casapalca
dc.typeTesis


Este ítem pertenece a la siguiente institución