dc.contributor | Del Savio, Alexandre Almeida | |
dc.contributor | Tuesta Schuler, Rodrigo (Ingeniería Civil) | |
dc.contributor | Vicuña Jimenez, Mark Anthony (Ingeniería Civil) | |
dc.creator | Tuesta Schuler, Rodrigo | |
dc.creator | Vicuña Jimenez, Mark Anthony | |
dc.creator | Del Savio, Alexandre Almeida | |
dc.creator | Palpan, Alejandro | |
dc.creator | Quiroz, Felipe | |
dc.creator | Valle, Erika | |
dc.date.accessioned | 2023-10-12T16:51:36Z | |
dc.date.accessioned | 2024-05-08T12:53:21Z | |
dc.date.available | 2023-10-12T16:51:36Z | |
dc.date.available | 2024-05-08T12:53:21Z | |
dc.date.created | 2023-10-12T16:51:36Z | |
dc.date.issued | 2022 | |
dc.identifier | Rodrigo Tuesta, R., Vicuña, M., Del Savio, A. A., Palpan, A., Valle E. & Quiroz, F. (2022). Prefabricated Reinforcement in Construction Using VDC: Case Study Ovalo Monitor Bridge. In Proceedings of the 2022 30th Annual Conference of the International Group for Lean Construction, IGLC 2022, Edmonton, Canadá, July 2022, 1008-1019. https://doi.org/10.24928/2022/0210 | |
dc.identifier | https://hdl.handle.net/20.500.12724/19080 | |
dc.identifier | 30th Annual Conference of the International Group for Lean Construction, IGLC 2022 | |
dc.identifier | https://doi.org/10.24928/2022/0210 | |
dc.identifier.uri | https://repositorioslatinoamericanos.uchile.cl/handle/2250/9354872 | |
dc.description.abstract | In construction projects, there may be rework and delays associated with construction processes with a low level of industrialization, resulting from the lack of constructability of the designs. To promote industrialization and improve the project's constructability, we implemented the Virtual Design & Construction (VDC) methodology, combined with a system of prefabricated reinforcement cages (PRC) elements in constructing an 870-meter span bridge located in Lima, Peru. The objective was to reduce structural rebars' assembly times, replace the traditional on-site processes of cutting, bending, and assembling steel with an industrial process based on systems of PRC steel elements. As a result, the assembly times of the structural item were reduced by 31%, thanks to the use of PRC elements. In addition, due to the VDC methodology, a 100% buildable design of the PRC elements was achieved. | |
dc.language | eng | |
dc.publisher | The International Group for Lean Construction | |
dc.publisher | CA | |
dc.rights | https://creativecommons.org/licenses/by-nc-nd/4.0/ | |
dc.rights | info:eu-repo/semantics/openAccess | |
dc.source | Repositorio Institucional - Ulima | |
dc.source | Universidad de Lima | |
dc.subject | Pendiente | |
dc.title | Prefabricated
Reinforcement in Construction Using VDC: Case Study Ovalo Monitor Bridge | |
dc.type | info:eu-repo/semantics/conferenceObject | |