Article
Diseño de un sistema de tratamiento para las aguas residuales del camal municipal del cantón Girón
Fecha
2023-04-12Autor
Ordóñez Pesántez, Patricia Elizabeth
Quezada Ibarra, Santiago Juvenal
Institución
Resumen
Girón’s municipal slaughterhouse has a wastewater treatment system with a grid and two
tanks for solids separation, which is not enough for a proper effluent treatment. Because of it,
this work’s objective was to develop a design proposal for a wastewater treatment plant
(WWTP) for this slaughterhouse. In order to that, three sampling campaigns and a
characterization of the wastewater in the laboratory were carried on, the analyzed parameters
were: total suspended solids (TSS), total nitrogen (NT), total phosphorus (P), biochemical
oxygen demand (BOD5), chemical oxygen demand (COD), fats and oils, fecal coliforms (FC)
and total coliforms (TC), these data were compared with the TULSMA environmental
regulations. Through the bibliographic review, theoretical removal efficiencies were
established, according to the treatment unit. Using the information of the physical space
available in the establishment and the population growth, three different treatment options
were sized and designed. The effluent characterization showed that the parameters: FC
(1.20E+04NMP/100ml), BOD5 (13mg/l), COD (214 mg/l), TSS (1200mg/l) CF, exceeded the
regulated permissible limit, which stablishes: FC (1.20E+04NMP/100ml), BOD5 (13mg/l), COD
(214 mg/l), TSS (1200mg/l) respectively. Finally, according to the theoretical removal
efficiencies and those calculated with CapdetWorks, it was established that the number 3
treatment option (grids, equalization tank, grease trap, coagulation/flocculation and Upflow
Anaerobic Sludge Blanket 'UASB') is the adequate, since it occupies an area of 23.03 m2,
which is within the usable area in the establishment (34.73 m2), in addition to the fact that
BOD5 is the base parameter for the design, this option presented a high BOD5 removal
efficiency (94.20% calculated and 86.74% modeled).