dc.contributor | Rea Andrade, Hartman Adolfo | |
dc.creator | Eras Guamán, Jorge Armando | |
dc.date.accessioned | 2022-04-07T21:25:45Z | |
dc.date.accessioned | 2023-03-09T17:27:35Z | |
dc.date.available | 2022-04-07T21:25:45Z | |
dc.date.available | 2023-03-09T17:27:35Z | |
dc.date.created | 2022-04-07T21:25:45Z | |
dc.date.issued | 2002-10-11 | |
dc.identifier | http://repositorio.ug.edu.ec/handle/redug/59206 | |
dc.identifier.uri | https://repositorioslatinoamericanos.uchile.cl/handle/2250/6088979 | |
dc.description.abstract | El objetivo principal por el cual se desarrollo el tema, es de disminuir las perdidas económicas
que afectan a la constructora.
Para la identificación de los problemas se ha utilizado dos herramientas de Ingeniería como es
el diagrama Causa-Efecto y el de Pareto, ya que con la ayuda de estos diagramas hemos
podido cuantificarlos y saber la incidencia económica que afecta.
Entre los problemas más importantes que se ha encontrado son los siguientes:
Reprocesos de productos de mala calidad.
Retrasos de transporte de recursos
Paralización de maquinas y equipos
Para dar solución a los problemas se ha comparado las perdidas económicas actuales con la
inversión que se va a realizar tomando en cuenta el tiempo en que se va recuperar la inversión.
De lo antes enunciado se puede concluir que solucionando los problemas de mayor índice
económico la constructora puede brindar productos de mejor calidad y entrega de los
contratos en el menor tiempo posible.
Se recomienda poner en practica las soluciones planteadas para así disminuir las perdidas
económicas. | |
dc.description.abstract | The main objective for which the topic was developed is to reduce economic losses
that affect the construction company.
For the identification of the problems, two engineering tools have been used, such as
the Cause-Effect diagram and the Pareto diagram, since with the help of these diagrams we have
been able to quantify them and know the economic impact they affect.
Among the most important problems that have been found are the following:
Reprocessing of poor quality products.
Resource Transport Delays
Shutdown of machinery and equipment
To solve the problems, the current economic losses have been compared with the
investment to be made taking into account the time in which the investment will be recovered.
From the foregoing, it can be concluded that solving the problems with the highest index
economically, the construction company can provide better quality products and delivery of the
contracts in the shortest possible time.
It is recommended to put into practice the proposed solutions in order to reduce losses
economic. | |
dc.language | spa | |
dc.publisher | Universidad de Guayaquil. Facultad de Ingeniería Industrial. Carrera de Ingeniería Industrial. | |
dc.relation | ;BINGI2706 | |
dc.rights | openAccess | |
dc.subject | GESTIÓN DE LA PRODUCCIÓN | |
dc.subject | DISMINUCIÓN DE REPROCESOS | |
dc.subject | RETRASOS EN PRODUCCIÓN | |
dc.subject | CONSTRUCCIÓN | |
dc.title | Disminución de reprocesos y retrasos en la ejecución de la producción en Constructora Ferrero Cía. Ltda. | |
dc.type | Thesis | |