Artículo de revista
Gestión de Proyectos con Teoría de Restricciones aplicada al área técnica de la Compañía Construcciones y Servicios S. A.
Fecha
2014-05-13Registro en:
ISSN 28113854
Autor
Gómez-Posada, L. F. (Luis Felipe)
Jiménez-Villalobos, J. B. (Juan Bernardo)
Institución
Resumen
The Dinpro-Construcciones y Servicios group is oriented towards the design, construction, assembly
and maintenance of industrial and logistic projects; “Construcciones y Servicios” company
focuses in the construction, assembly, and maintenance of these projects; this article is developed
at this company. One of the most important activities within the execution of construction projects
is to ensure that the contractors are well prepared to execute that which was agreed, in the scheduled
moment and with the arranged characteristics, but to hire on time before the starting day of
the each activity depends of the work team. Nevertheless, there are no follow up and control tools
which allow assuring the efficacy of the hiring process so that it is done on time in the field. This
essay pretends to display the experience of “Construcciones y Servicios” S.A. in the application of
the solutions granted elements for the General Management of TOC Projects (Critical chain) to the
hiring process, executed as a project per se with successful results.